Color
Legend: RED= Open Blue= Closed |
|
|
|
|
|
|
|
|
|
|
|
|
Last
Updated |
############ |
|
|
|
|
|
|
|
PAR# |
Date recd |
Problem |
Person reporting |
Ind resp. |
Mgmt resp. |
Report due date |
PAR implem. Date |
Report complete |
PAR implemented |
Status |
Comments |
Report |
|
|
|
|
|
|
|
|
1 |
3/3/2006 |
While putting slit orders there can be a human error where
wide coil |
J. Rowe |
J. Rowe |
J.Rowe |
3/7/2006 |
3/7/2006 |
|
closed |
|
|
finish will not match with slit finish |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2 |
3/9/2006 |
Packing
of Hi carton, need a standard for all shifts, so packing is |
B. Frymoyer/ |
J. Laidig/ |
J. Laidig/ |
8/15/2006 |
8/15/2006 |
|
|
|
|
always the same. Too much time lost on this. |
M. Sweitzer |
M. Collur/ |
M. Collur |
Frymoyer to write instructions for each |
|
|
open |
|
|
|
|
B.Frymoyer |
|
item and give to John who will compile |
|
|
|
|
3 |
3/9/2006 |
At
recut, do lot of movement of long lengths due to due dates. This |
Tim Hagans |
R. Jungberg |
M. Watkins |
5/10/2006 |
|
|
open |
|
|
damages the product. |
|
|
Cost of racks to store and more warehouse space |
|
|
|
|
|
|
|
|
|
|
|
|
4 |
3/9/2006 |
3/8" or 1/2" sq long length shipouts too long, they
bend when you pick |
Tim Hagans |
R. Bishop/BW |
M. Watkins |
4/24/2006 |
|
|
open |
|
|
them up with tow motor |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5 |
3/13/2006 |
For Haworth, Std tube/Closetmaid orders and all customers in
general |
K. Veen |
M. Watkins/ |
M. Watkins |
5/10/2006 |
|
|
open |
|
|
Sales asks shipping to ship, but shipping cannot find the
product. |
|
S. Loos |
|
|
|
|
|
|
This leads to orphaned material, FG and excess shippping
expenses |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
6 |
3/13/2006 |
Roof leak or a clogged gutter in area A-16 (MTS warehouse),
causing |
B. Hofmann |
S. Capiottis |
M. Watkins |
4/24/2006 |
|
|
open |
|
|
damage to material
in this area. |
|
|
|
|
|
|
|
` |
|
|
|
|
|
|
7 |
4/6/2006 |
9
mill buttwelder must be replaced - it works borderline at best and on |
B. Miller |
B. Miller |
M. Watkins/ |
5/6/2006 |
6/6/2006 |
|
closed |
|
|
heavy gage does not work |
|
S. Capiotis |
|
|
|
|
|
|
|
|
|
|
|
|
8 |
4/6/2006 |
#3 mill alignment problem-operator having difficulty aligning
weld and |
Bruce Miller |
B. Walters/Strat |
B.Walters |
7/1/2006 |
Sladky's report done, need plan to implement |
|
|
|
|
maintaining good weld |
|
& Sladky |
|
|
|
|
|
|
|
|
|
|
|
|
9 |
3/23/2006 |
Slit order 18994 does not state if all slits or any slits
belong to 1800 |
Don Glass |
J. Rowe |
B. Hofmann |
3/31/2006 |
4/7/2006 |
Y (4/12/06) |
|
closed |
|
|
Need to clarify whether to skid or put in bins |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10 |
3/25/2006 |
Lack of end machine dedicated to 4 mill causing undue downtime |
BS (8188) |
R. Bishop |
M. Watkins |
5/24/2006 |
Now that we have retrofit reamer, we have dedicated wire brush |
|
closed |
|
|
fixing up machines from other mills |
|
|
|
reamers on each mill. Need to ensure PM is performed on them |
|
|
|
|
|
|
|
|
|
|
|
11 |
3/25/2006 |
4 mill's 1.375" rolls are old and shot, giving ovality
problems |
BS (8188) |
B. Walters |
R. Bishop |
5/5/2006 |
1.375" rd will be scheduled on M2 mills with better
tooling |
|
closed |
|
|
|
|
|
|
|
|
|
12 |
3/25/2006 |
4 mill's 1.75"rd rolls are shot, ovality problems |
BS (8188) |
B. Walters |
R. Bishop |
5/5/2006 |
New rolls expected 7/14 should solve this problem |
|
closed |
|
|
|
|
|
|
|
|
|
13 |
3/25/2006 |
4mill's 610 oval rolls not ground properly - concavity
problems - newset? |
BS (8188) |
B. Walters |
R. Bishop |
5/5/2006 |
Report
recd from Bruce. Short footage of 100,000 ft per yr does not warrant purchase
of new rolls. |
|
closed |
|
|
|
|
|
|
Customer willing to take parts in current condition |
|
|
|
14 |
3/25/2006 |
Bench exhaust units need to be checked for proper flow. At any
time |
|
|
|
|
|
|
|
at any mill especially #1 mill , smoke billows out into the
dept. |
Fick (2297) |
B. Walters |
R. Bishop |
5/5/2006 |
Work order completed 7/12/06 |
|
closed |
|
|
Status: WO 29730
cleaning during shut down, currently in working condition |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
15 |
3/25/2006 |
Floor at 1 mill has deep holes. We run 20" tubing and
balance it on one |
Joe Elacqua |
Leroy/Robin Bishop |
|
|
Floor was
cleaned and holes were patched over shut down. |
|
closed |
|
|
|
fork.Bander takes chance balancing it. If the truck will hit
the hole, skid |
|
|
|
A quote to resurface area |
|
|
|
|
will fall. |
|
|
|
around cutoff and front of drop table is being pursued by
Strat of mtce. |
|
|
|
|
|
|
|
|
|
|
|
16 |
3/20/2006 |
Floor at #1 mill has deep holes. We run 20" tubing and
balance it on 1 |
Zimmerman/Fick |
R. Bishop |
Zimmer/Fick |
4/28/2006 |
|
4/28/2006 |
|
closed |
|
|
fork. |
|
|
Zimmerman/Fick to stop the spills as floor was fixed last
year. |
|
|
|
|
|
|
|
|
|
|
|
|
17 |
3/20/2006 |
Cover plate on ream#1 not attached properly |
Zimmerman/Fick |
R. Bishop |
R. Bishop |
4/28/2006 |
|
5/2/2006 |
|
closed |
|
|
|
|
Per Robin, mtce work order 29717 was
submitted and completed as of 4/26/06 |
|
|
|
|
|
|
|
|
|
|
18 |
3/25/2006 |
Payoff wheel very hard to turn at 4 mill. Could cause injury |
BS |
R. Bishop |
R. Bishop |
5/5/2006 |
|
5/2/2006 |
|
closed |
|
|
|
|
Submit a mtce WO |
Per Robin, completed by Mtce without work order on 4/17/06 |
|
|
|
19 |
3/30/2006 |
Bump marks in 1400 for item 1045676 |
Daniel Dougherty |
M. Watkins |
report by Mike sent to
Mike Krout to be given to 1400 personnel |
Per Mike, this was addressed with the crew |
|
closed |
|
|
|
|
|
|
|
|
|
20 |
3/30/2006 |
Bump marks in 1400 for item 1045676 |
Tom Wertz |
M. Watkins |
report by Mike sent to
Mike Krout to be given to 1400 personnel |
Per Mike, this was addressed with the crew |
|
closed |
|
|
|
|
|
|
|
|
|
21 |
3/30/2006 |
Bump marks in 1400 for item 1045676 |
Mike Julian |
M. Watkins |
report by Mike sent to
Mike Krout to be given to 1400 personnel |
Per Mike, this was addressed with the crew |
|
closed |
|
|
|
|
|
|
|
|
|
22 |
3/30/2006 |
Lack of supervision on 1st shift at 1400 |
entire 2nd shift |
M. Watkins |
report by Mike sent to
Mike Krout to be given to 1400 personnel |
Mike Watkins to send a report to 2nd shift employees |
|
closed |
|
|
|
|
|
|
|
|
|
23 |
3/30/2006 |
Bump marks on 86488, mgmt continues to run line despite
problems |
Jan Pilat (5978) |
M. Watkins |
report by Mike sent to
Mike Krout to be given to 1400 personnel |
|
closed |
|
|
|
|
|
|
|
|
|
24 |
3/30/2006 |
Steel certification: Steel should be certified before it is
run on mills. If it is not |
S. Loos |
B. Hofmann/ |
5/1/2006 |
5/15/2006 |
Robin putting a code "NOC" |
7/1/2006 |
7/1/2006 |
closed |
|
|
|
certified, then it should be tagged a suspect so shipping
knows that it cannot |
|
S. Benner |
|
|
for slits/coils without certs |
|
|
|
|
|
be shipped. This could prevent shipping from accidentally
shipping an order |
|
|
|
Jim will not schedule this |
|
|
|
|
|
that needs mill certs for it. |
|
|
|
steel for customers needing certs |
|
|
|
|
|
|
|
|
|
|
|
|
25 |
3/30/2006 |
Benington item is racked under larger items, drip marks? |
Edinger (1744) |
M. Watkins/Eric |
5/1/2006 |
5/15/2006 |
|
|
open |
|
|
Run under 2500 to avoid drip marks? |
|
|
|
|
|
|
26 |
3/30/2006 |
Head speed needs to be repaired for Chevalier mill |
L. Mays (4990) |
Strat |
6/30/2006 |
6/30/2006 |
|
|
open |
|
|
|
|
|
|
|
|
|
27 |
3/30/2006 |
Ways need to be trued up (cuts taper) - Clausing lathe |
L. Mays (4990) |
Strat |
6/30/2006 |
6/30/2006 |
|
Put a capital for $3000,
waiting for |
open |
|
|
|
|
|
|
approval |
|
|
|
28 |
3/30/2006 |
X-Y-Z ways need to be turned up (digital readout would improve
accuracy) |
L. Mays (4990) |
Strat |
6/30/2006 |
6/30/2006 |
|
|
open |
|
|
|
|
|
|
|
|
|
29 |
3/30/2006 |
All 0.014 steel for plating has spots/freckles in raw mostly
with 0.865 OD |
Edinger (1744) |
W. Lamma/ |
Receiving inspection |
6/30/2006 |
6/30/2006 |
10/3/2006 |
10/3/2006 |
open |
|
|
|
|
M. Collur |
given to Edinger |
|
|
|
|
30 |
3/30/2006 |
Pressing 6B, 42,5A, 10A - Presses are too low to ground -raise
them/ergonomics |
S.Traupman(8428) |
Ralph J |
|
4/14/2006 |
4/28/2006 |
|
open |
|
|
|
|
|
|
|
|
|
31 |
3/30/2006 |
Floor uneven back at slitter going out into crane |
JR (6578) |
Strat |
Put in a cap. Request |
4/29/2006 |
4/29/2006 |
|
open |
|
|
|
|
waiting for approval |
|
|
|
|
32 |
3/30/2006 |
Floor uneven at 4 mill upender |
John R (6578) |
R.Bishop/ |
M.Watkins/Strat |
|
|
open |
|
|
|
|
L. Knabb |
|
|
|
|
|
33 |
3/30/2006 |
Had to wipe rust off and wip oil on tube and reskid
(Inter-7073) |
JR (6578) |
R. Bishop/ |
M.Watkins/Strat |
5/1/2006 |
5/31/2006 |
|
open |
|
|
Columbia (10698) - tube rusting due to floor leaking (wood
shop section4) |
Hauz(3015) |
L. Knabb |
|
|
|
|
|
|
|
|
|
|
|
|
|
34 |
3/30/2006 |
Poor
management not enough people on 2nd shift to cover when |
Bill Frymoyer |
B. Miller |
Bob Miller said jobs have
been posted. We need to hire and train more people |
closed |
|
|
someone is out |
2539 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
35 |
3/30/2006 |
Raw material/tubes from department 700 in recent weeks have
lot of defects |
Edinger (1744) |
R. Bishop |
Mike assigned to Bishop |
6/30/2006 |
6/30/2006 |
|
open |
|
|
|
|
|
|
|
|
|
36 |
3/30/2006 |
Rails
are turned without the bolt on the inside. They catch the bottom |
Edinger (1744) |
Eric/Bob J |
Mike assigned to Eric/Bob |
|
|
open |
|
|
of cranes causing wrecks, lost production and cause material
to sit |
|
|
|
|
|
|
|
in the tanks longer than its good for them until wreck is
cleared. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
37 |
3/30/2006 |
Tubles smaller than 20" need to go into double skids.
Moving shorter |
Edinger (1744) |
Bob Jungberg |
Mike assigned to Eric |
6/30/2006 |
6/30/2006 |
|
open |
|
|
lengths in singles are more likely fall off the forks and be
damaged |
|
|
|
|
|
|
|
in department while shipping |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
38 |
3/30/2006 |
Lot of complaints on 1 mill due to scratches. Examine root
cause as |
Fick (2297) |
Strat |
Mike assigned to Strat |
6/30/2006 |
6/30/2006 |
|
open |
|
|
contaminated coolant. If we screen coolant returning to
recovery tank |
|
|
|
|
|
|
|
through a large magnet will help scratches |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
39 |
4/5/2006 |
Catwalk ramp between cutoff and sizing gets slippery from
cooland/oil |
Alex Donkel (1140) |
Strat |
Mike Watkins |
6/30/2006 |
6/30/2006 |
|
open |
|
|
(suggestion: put a friction pad or rubber mat fastened to
catwalk) |
|
assigned to |
|
|
|
|
|
|
|
Strat |
|
|
|
|
40 |
3/30/2006 |
Reamer and Swager rate sheet#3 new chart, parts are missing
now |
Charlie E. Carlisle |
J. Laidig |
John Laidig gave new 1800
ream and swage rate sheets to Charlie and also added rated. |
closed |
|
|
|
(1062) |
|
for over 85 cuts per min |
|
|
|
|
|
|
|
|
|
|
|
|
41 |
4/17/2006 |
700 mtgs to be held in west conference room as there are
interruptions |
Fick |
R. Bishop |
|
6/30/2006 |
6/30/2006 |
Conference room will be
used as |
closed |
|
|
in grind room |
|
|
|
required, will have mtgs
in grind room |
|
|
|
|
|
|
|
|
|
42 |
4/17/2006 |
Quality statement sheets to be hung at time
clocks-restrooms-locker |
Fick |
M. Collur |
|
6/30/2006 |
6/30/2006 |
More quality policy
statements |
closed |
|
|
rooms |
|
|
|
have been posted in
lunchroom etc |
|
|
|
|
|
|
|
|
|
43 |
4/17/2006 |
Look at 1500-1.187" M2.5 RK5-96 rolls on rack not being
used - rack |
Fick |
B. Walters |
|
6/30/2006 |
|
|
open |
|
|
congested, remove rolls that are not being used |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
44 |
4/17/2006 |
Can data plate be installed on all square tubing torque head ,
this might |
Fick |
B. Walters |
|
6/30/2006 |
6/30/2006 |
|
open |
|
|
alleviate some of the guess work |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
45 |
4/17/2006 |
Holes are punched with tabs bent over toward tap handle -
coating |
M. Krout (4328) |
Ralph J |
Punch is changed |
6/30/2006 |
6/30/2006 |
7/1/2006 |
7/1/2006 |
closed |
|
|
Costing hooks do not seat properly - solution rotate punch to
have tabs |
|
|
|
|
|
|
|
bend over to bottom (toward leg end) - item 1046796 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
46 |
4/21/2006 |
Reamer pin at 1 mil having lot of trouble on one mill from
remaer or |
Fick |
Robin B |
|
6/30/2006 |
6/30/2006 |
|
open |
|
|
roller marks |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
47 |
5/5/2006 |
Scheduling dept puts short 2" diameter lengths on 4 mill.
The result is |
Mike Dunkle |
Bill H, Robin B |
|
6/15/2006 |
6/15/2006 |
Lakewood item will be recut
going |
closed |
|
|
cut off jaws are damaged beyond repair. |
(1554) |
|
|
|
forward. Routings
changed. |
|
|
|
|
|
|
|
|
|
|
48 |
5/9/2006 |
Can bushes be trimmed along parking are by employment office |
Fick |
Not valid PAR |
|
|
|
closed |
|
|
|
|
|
|
|
|
|
49 |
5/9/2006 |
Catwalk ramp on 6 mill gets oil and coolant spray on them
making it |
Alex Donkel |
Robin B/Strat |
|
6/30/2006 |
6/30/2006 |
|
open |
|
|
extremely slippery |
(1140) |
2 work orders put in by Robin |
|
|
|
|
|
|
soln: Put rubber mats on rampls or some kind of friction pads |
|
3rd work order on 6/8/06 # 30379 |
|
|
|
|
|
|
|
|
|
|
|
|
|
50 |
5/12/2006 |
Powder
coating, Graco 85372, Fix source of problem in 1100, not in 1400, |
Dan Dougherty |
Ralph J/Mike K/Jay C |
|
6/15/2006 |
6/15/2006 |
Jay provided a report |
closed |
|
|
makign 1400 employees do 1100 problem (grease on tube) |
(1547) |
|
|
|
mfg/scheduling to utilize
report recommendations to prevent this problem |
|
|
|
|
|
|
|
|
51 |
5/19/2006 |
Benington packaging: High quality tubes getting no paper, no
cardboard |
Edinger (1744) |
S. Gallagher |
|
6/15/2006 |
6/15/2006 |
Steve G wrote a note saying |
closed |
|
|
on bottom, where the lift fork rubs against. |
|
|
|
customer wants to try it
due to their automated shop |
|
|
|
|
|
|
as operators do not have time to
remove paper |
|
52 |
5/19/2006 |
Positioning racking od drop pin work on our plating racks -
lots of drips |
Edinger (1744) |
Eric B/Bob J |
|
6/30/2006 |
6/30/2006 |
|
open |
|
|
and slop marks |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
53 |
7/28/2006 |
Tractor Trailer fumes during winter months when truck are
warmed up. Fumes |
Fick |
M. Watkins |
M. Watkins |
10/31/2006 |
10/31/2006 |
|
open |
|
|
are ventilating inside building. Need vent hood in 1400 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
78 |
8/12/2006 |
Tubing
for item 1046139, Melnor was rusty, paint chips, light coating, bump |
Chris Garber |
M. Krout |
M. Watkins |
10/31/2006 |
10/31/2006 |
|
open |
|
|
marks,ring
gage did not fit, supervisor was informed of defects, but employee was |
|
|
|
|
|
|
|
instructed to continue, loading and coating |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
79 |
8/16/2006 |
Scouring of cutoff knifes. If knives were changed before
scouring got too bad, |
David Breidgian |
R. Bishop/ |
R. Bishop/ |
10/31/2006 |
10/31/2006 |
Routing change completed
for all |
closed |
|
|
they could be sharpened. The scoured ones can be used for
recut orders |
|
B. Walters |
M. Watkins |
|
stack items - change
cutoff knife |
|
|
|
(we have many). Gary shultz did this on 5 mill tear drop every
3 hrs |
|
|
|
every 10000 cuts |
|
|
|
|
|
|
|
|
|
|
80 |
8/14/2006 |
Somebody should check gage from beginning to end before we
accept slit steel |
H. Stamm |
M. Collur/ |
M. Collur/ |
10/2/2006 |
10/2/2006 |
Response given to
operators with our |
closed |
|
|
from outside with special reference to SLS steel |
M. Schammauer |
B. Lamma |
B. Lamma |
|
Receiving inspection
procedure. Do not inspect slit steel. |
|
|
|
|
|
Requested B. Lamma to
track supplier metrics/rejects |
|
|
|
|
|
|
|
|
|
81 |
8/22/2006 |
Rust from drips and from sitting waiting for next process |
Chris Garber |
B. Hofmann/ |
M. Collur |
9/30/2006 |
9/30/2006 |
PAR report submitted to
C. Garber |
closed |
|
|
Summo blanket order or stock order being run too soon. Order
sit for too long |
|
P. Sweigart |
|
|
Back scheduled dates ok |
|
|
|
and sometimes under pipes that drip. Causing rust. Sometimes
rust is small |
|
|
|
Customer service will maintain
due |
|
|
spots. Solution: runs orders at mills only when needed/ The
less time between |
|
|
|
dates, will not change
dates once |
|
|
|
processes the better. |
|
|
|
product is produced off
the mill |
|
|
|
|
|
|
|
|
|
|
82 |
8/22/2006 |
Tickets not correct. After process, no new ticket is made.
Tickets still read |
Chris Garber |
M. Collur/ |
M. Collur |
9/30/2006 |
9/30/2006 |
|
closed |
|
|
119.00
inches rather than finished length. Scratched out order # with no date |
|
B. Hess |
|
|
|
|
|
|
or initials. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
83 |
9/12/2006 |
Cost Saving: Instead of ordering new top rolls, send example.
2. 1000 2. .865 rolls |
David Breidigan |
R. Jeshoneck |
Ralph T. |
9/30/2006 |
2/21/2007 |
New roll is cheaper than
ID |
closed |
|
|
to roll kraft and have I.D.s chromed. |
|
M. Watkins |
|
|
chroming |
|
|
|
|
|
|
|
|
|
|
|
84 |
9/20/2006 |
Excessive Rust. Increase coolant checks, install tube dryers
at all mills to stop |
Fick |
R. Bishop |
R. Bishop |
10/15/2006 |
10/15/2006 |
|
open |
|
|
excessive water being pulled through sizing and tube oiler.
Contact Roll Kraft or |
|
M. Watkins |
|
|
|
|
|
|
or different oiler. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
85 |
9/29/2006 |
5 mill or any mill not being able to see the problem with
naked eye. My idea is to video |
Fick |
R. Bishop |
R. Bishop |
10/31/2006 |
10/31/2006 |
|
open |
|
|
record
5 mill at the end finisher. This would allow the tape to be slowed down and
root |
|
|
|
|
|
|
|
cause be identified
immediately. This would take out all the guess work with the problem |
|
|
|
|
|
|
|
of jam ups and down time. Note: If idea is accepted, please
notify union officials |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
102 |
9/27/2006 |
Safety:
The yellow wooden ladder marked "1 700 looper" is missing the
non-slip rubber |
David Breidigan |
|
9/27/2006 |
|
open |
|
|
feet. It is now metal on concrete. |
|
|
|
|
|
|
|
|
|
103 |
9/29/2006 |
.750 Square rack needs new wheels. |
William D. |
|
|
9/29/2006 |
|
|
open |
|
|
|
|
|
|
|
|
|
104 |
10/26/2006 |
Operators
doing millwright work or electrical work not knowing what they are doing (not |
Anonymous |
R. Bishop |
|
|
|
open |
|
|
qualified). |
(no name -could be |
|
|
|
|
|
|
|
Do not let operator do maintenance on machines. They do not
know what to do or how to do it |
from 700) |
|
|
|
|
|
|
|
They just try, but end up all messed up |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
116 |
10/26/2006 |
Scrap (problem): Hire more QA people to monitor mills only. Do
not ,et mill operator run order |
Anonymous |
R. Bishop |
|
|
|
open |
|
|
until QA person signs off |
(no name -refers to |
|
|
|
|
|
|
|
|
mills hence 700) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
128 |
11/15/2006 |
Scouring of knifes: change knives more often to avoid
scouring. As is being done on |
D. Breidigan |
R. Bishop |
M. Wattkins |
1/15/2007 |
1/15/2007 |
|
open |
|
|
#5 mill tear drop. It is working, grinding can sharpen and
resharpen knives repeatedly |
|
R. Bishop |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
129 |
11/17/2006 |
Scouring of knifes: change knives more often to avoid
scouring. As is being done on |
D. Breidigan |
R. Bishop |
M. Wattkins |
1/15/2007 |
1/15/2007 |
|
open |
|
|
#5 mill tear drop. It is working, grinding can sharpen and
resharpen knives repeatedly |
|
R. Bishop |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|